SREDA | National Database of Renewable Energy

Project/System ID Number: 127

Item Name Information
System Name : 30MW (AC) Solar Park by Intraco CNG Ltd & Juli New Energy Co. Ltd.
System ID : SID # 127
Technology Type : Solar Park
Grid Status : On Grid
Capacity : 30 MWp
Completion Date : 2022-08-28
Present Status : Completed & Running
System Owner : Not Found
EPC : Not Found
Financing Org. : Independent Power Producer (Unsolicited) (IPP (Unsolicited))
Inserted by : Tapos Kumar Saha (31)
Creation Date : 2016-09-22 12:26:15
Updated by : Eratosh Chakma (273)
Modification Date : 2022-10-24 21:07:19
Item Name Information
Implementing Agency : Bangladesh Power Development Board (BPDB)
Office/Program : -
PD Name : .
Division : Rangpur
District : Rangpur
Upazilla : Gangachara
Location : Gangachara
Latitude, Longitude : 25.855312, 89.222482
Note : COD Date Entry
Expected Energy Generation and CO2 Emission reduction during System Life : 654 GWh, 309 k tCO2
Expected Energy Generation and CO2 Emission reduction till today : 74 GWh, 35 k tCO2
 