SREDA | National Database of Renewable Energy
Project/System ID Number: 152
Item Name |
|
Information |
System Name |
: |
Sonagazi 75 MW Solar Power Plant Construction Project |
System ID |
: |
SID # 152 |
Technology Type |
: |
Solar Park |
Grid Status |
: |
On Grid |
Capacity |
: |
75 MWp |
Completion Date |
: |
2024-04-01 |
Present Status |
: |
Completed & Running |
System Owner |
: |
Electricity Generation Company of Bangladesh (EGCB) (42) |
EPC |
: |
Not Found |
Financing Org. |
: |
World Bank (WB) |
Inserted by |
: |
Tapos Kumar Saha (31) |
Creation Date |
: |
2016-09-24 11:31:01 |
Updated by |
: |
MD. Shahidul Quddus (285) |
Modification Date |
: |
2024-05-02 09:30:41 |
|
Item Name |
|
Information |
Implementing Agency |
: |
Electricity Generation Company of Bangladesh Ltd. (EGCB) |
Office/Program |
: |
- |
PD Name |
: |
Mohammad Anwar Hossain |
Division |
: |
Chittagong |
District |
: |
Feni |
Upazilla |
: |
Sonagazi |
Location |
: |
Purba Boro Dholi |
Latitude, Longitude |
: |
22.791058, 91.366944 |
Note |
: |
EPC Contract Signed on 15 Jun 21 with Trina-HYDC JV (JV of Changzhou Trina Intelligence Energy Engineering Ltd., China (Lead Partner) and Zhejiang Huayun Electric Power Engineering Design and Consultation Co., Ltd., China) |
Expected Energy Generation and CO2 Emission reduction during System Life |
: |
2 TWh, 773 k tCO2 |
Expected Energy Generation and CO2 Emission reduction till today |
: |
46 GWh, 22 k tCO2 |
|
|
|