SREDA | National Database of Renewable Energy
Project/System ID Number: 5747
Item Name |
|
Information |
System Name |
: |
200 MW (AC) Grid-Tied Solar PV Power Plant By Consortium of Parker Bangladesh Limited & Sumitomo Corporation |
System ID |
: |
SID # 5747 |
Technology Type |
: |
Solar Park |
Grid Status |
: |
On Grid |
Capacity |
: |
200 MWp |
Completion Date |
: |
2027-07-09 |
Present Status |
: |
Under Planning |
System Owner |
: |
Not Found |
EPC |
: |
Not Found |
Financing Org. |
: |
Independent Power Producer (Unsolicited) (IPP (Unsolicited)) |
Inserted by |
: |
Eratosh Chakma (273) |
Creation Date |
: |
2024-02-06 15:51:37 |
Updated by |
: |
- |
Modification Date |
: |
- |
|
Item Name |
|
Information |
Implementing Agency |
: |
Bangladesh Power Development Board (BPDB) |
Office/Program |
: |
- |
PD Name |
: |
|
Division |
: |
Rangpur |
District |
: |
Dinajpur |
Upazilla |
: |
Parbatipur Upazila |
Location |
: |
Barapukuria |
Latitude, Longitude |
: |
25.540556, 88.97025 |
Note |
: |
Project Data Entry |
Expected Energy Generation and CO2 Emission reduction during System Life |
: |
4 TWh, 2 M tCO2 |
Expected Energy Generation and CO2 Emission reduction till today |
: |
0 kWh, 0 gCO2 |
|
|
|